BRIDGE CLOSURE - IDOT CHICAGO AVENUE OVER IL ROUTE 83 BRIDGE DECK REPAIR PROJECT
IDOT has scheduled bridge deck repairs for the summer of 2020. The general scope of work includes bridge repairs, joint repair, latex overlay and incidental and collateral work necessary to complete the project. This will require a complete closure of the bridge. IDOT has indicated the detour route will be Ogden Avenue and the detour for thru traffic will be posted for Cass Avenue and for Madison in Hinsdale. This project may also require lane reductions on Route 83 to complete the necessary work on the underside of the bridge. IDOT anticipates needing 30 days to complete the work. Work is scheduled to start on May 18th.